When Is A Data Center Success Story Not A Success Story?


Posted by John Soat, Aug 4, 2008 02:33 PM

When a state auditor's report blasts the project, and politicians start playing football. Oregon's data center consolidation project is a cautionary tale about either a lack of careful project management or carefully managing expectations -- probably both.


As part of its ongoing "CIOs Uncensored" feature series, InformationWeek published an article on July 21 about the state of Oregon's data center consolidation project, written by the director of the data center, Mark Reyer. While the article mentioned problems with the project, in particular related to the cultural issues of working with 11 state agencies and their formerly independent IT organizations, it was generally a positive review of what had been accomplished.

Several days before publication, the Office of the Secretary of State issued an auditor's report critical of the data center consolidation project. When InformationWeek started to receive letters and online comments about the article, the project, and the auditor's report, we wrote our own story about the controversy.

So what's going on in Oregon?

The auditor's report says several "significant objectives" of the project have not been met, including sufficient progress in consolidation, functioning service level agreements, and an overall project management framework. Because resources will have to be added to the project, the hoped-for cost-savings probably won't materialize. And promised improvements in disaster recovery and security haven't been accomplished.

Reyer's response to the auditor's report is that it was written before significant progress had been made. Because a decision was made to move processing chores into the data center before the consolidation work had been completed, data center management essentially has been doing two things at once. Many of the objections in the report have been -- and continue to be -- addressed.

State legislators have become involved, as might be expected in a multimillion-dollar government project. Oregon's House Republican leader defends the project, but the head of the Information Technology Committee, a Democrat, has called a meeting to discuss it.

Systems integration projects almost always are costlier, more complicated, and take longer than anticipated. Is Oregon's a case of gross incompetence, or simply the vicissitudes typical of big IT projects?

If you know anything about the Oregon data center project, e-mail me at jsoat@techweb.com, or offer your comments below. If you have experience with -- opinions about -- the complications inherent in big systems integration projects, share them with us.

« Want Caller ID With Super Powers? Try Privus Mobile | Main | Hacking Nukes »



Sign Up Now
For InformationWeek News Alerts




This is a public forum. United Business Media and its affiliates are not responsible for and do not control what is posted herein. United Business Media makes no warranties or guarantees concerning any advice dispensed by its staff members or readers.

Community standards in this comment area do not permit hate language, excessive profanity, or other patently offensive language. Please be aware that all information posted to this comment area becomes the property of United Business Media LLC and may be edited and republished in print or electronic format as outlined in United Business Media's Terms of Service.

Important Note: This comment area is NOT intended for commercial messages or solicitations of business.




 
InformationWeek Chief Of The Year:
Call For Nominations
Know a dynamic, future-oriented tech chief? We're looking for the most insightful, innovative, forward-thinking business technology leader to honor as our 2008 Chief Of The Year. "Tomorrow's CIO" is the theme of our InformationWeek 500 Conference, and of a recent in-depth InformationWeek Analytics Report based on our extensive survey. The qualities identified with Tomorrow's CIO—equal parts leadership, vision, business savvy, technology expertise--are what we're looking for in our Chief Of The Year.

Candidates must be CIOs, CTOs, or VP-of-IT level executives. Nominations will be accepted now through Oct. 31, 2008.

Please send your nominations to: cjmurphy@techweb.com.



Sign Up For The CIOs Uncensored Newsletter
Every Thursday, Chris Murphy and his fellow analysts explore the business, strategy, and management issues most important to IT leaders.

Sign up for our free, weekly newsletter today!

Newsletter Archives


Global CIO Video

 

  1. It's all in the strategy, it's all about the design
  2. How To Do Parallelism Without Getting Egg On Your Face
  3. Managed Threads Are Different From Windows Threads


Join The InformationWeek Group On LinkedIn


  1. More Anti-Virus Fail
  2. Windows 7 Is Really That Good
  3. iPhone OS 4.0 Reported To Feature Multitasking


  1. Apple COO Awarded $22 Million Bonus
  2. FCC Site Measures Broadband Speeds
  3. B&N Plans App For Apple iPad
  4. Intel Previews 6-Core Processor
  5. Terracotta Upgrades Ehcache
  6. Data, Analysis Drive Maryland Government

 

  Ars Technica
Boing Boing
Channel 9 Forums
CRN Blogs
Dr.Dobb's Portal: Blogs
Engadget
Gizmodo
GrokLaw
  Lifehacker
Schneier on Security
Slashdot
TechCrunch
Techdirt
Techmeme
Valleywag

  DECEMBER 2008
NOVEMBER 2008
OCTOBER 2008
SEPTEMBER 2008
AUGUST 2008
JULY 2008
JUNE 2008
MAY 2008
  APRIL 2008
MARCH 2008
FEBRUARY 2008
JANUARY 2008
DECEMBER 2007
NOVEMBER 2007
OCTOBER 2007
SEPTEMBER 2007