Inside Interop 2011 Hot Stage

Start The Discussion  |  Mike Fratto  |  May 09, 2011 09:00 AM

Three months of planning the Interop network. Two weeks staging the equipment and preparing the network. Dozens of people from as many vendors all focused on putting together a network that will go live for six days. Glenn Evans, Interop network project lead and benevolent dictator, works with the vendors and volunteers to design, build, troubleshoot, and manage the InteropNet.

The hot stage is when all of the planning comes together. The InteropNet team documents every detail, down to where patch cords are connecting, ensuring that when the equipment is moved to the Mandalay Bay Convention Center in Las Vegas, it can be rolled to position, connected, and powered on in preparation for the exhibitors showing up and the show starting.

After the equipment is moved to the convention center, engineers check the equipment, reseating cables that might have come loose and fixing any problems that occurred. Much of the work after that involves running the network, including getting exhibitors connected and resolving any issues they may have.

Informationweek Discussions



InformationWeek encourages readers to engage in spirited, healthy debate, including taking us to task. However, InformationWeek moderates all comments posted to our site, and reserves the right to modify or remove any content that it determines to be derogatory, offensive, inflammatory, vulgar, irrelevant/off-topic, racist or obvious marketing/SPAM. InformationWeek further reserves the right to disable the profile of any commenter participating in said activities.

Disqus Tips To upload an avatar photo, first complete your Disqus profile. | View the list of supported HTML tags you can use to style comments. | Please read our commenting policy.