National Digital Archive Soaring Over Budget
The Electronic Records Archive project will cost 21% to 41% more than anticipated due to the lead agency's ineffective use of project management.A project by the National Archives and Records Administration (NARA) to creative a massive digital archive of electronic records is soaring over budget due to persisting project-management troubles, according to a federal watchdog agency.
More Government Insights
White Papers
- Creating the Enterprise-Class Tablet Environment - by Yankee Group
- New Visual and Wizard-Driven Paradigms for Exploring Data and Developing Analytic Workflows
Reports
More >>Webcasts
- Maximize ROI with Database Consolidation onto Private Clouds
- Server Virtualization Gets Relief From Tivoli Storage Manager for Virtual Environments
NARA Electronic Records Archive (ERA) will likely cost $1.2 billion to $1.4 billion when completed, exceeding the current $995 million estimated cost by 21% to 41%, according to a recent report by the Government Accountability Office (GAO). The agency blames the increased costs on the agency's ineffective use of a project-management technique aimed at making it easier, not harder, to manage a project.
NARA has been working on the ERA project since 2001 to preserve and provide electronic access to large volumes of government records. Lockheed Martin is the primary contractor on the project; the agency awarded the company a $317 million contract in 2005 to develop a contemporary digital archive for government records.
To help it manage the project, NARA has been using an approach called earned value management (EVM) that is meant to create objective reports of project status and anticipated completion costs if used properly.
However, the GAO said that NARA is mishandling its use of EVM because it lacks comprehensive EVM policy, training, and specialized resources. Moreover, it keeps re-planning the program, which also has complicated the management process.
The GAO and others in the past have criticized NARA for its handling of the project -- an inherently complex and unwieldy project, by any standards, that includes cooperation with multiple federal agencies. It's currently on the Office of Management and Budget's list of 26
For its part, Lockheed Martin said it's on schedule to complete its contract requirements by September 30 and will continue to work with NARA to address any GAO concerns "to ensure that tax dollars going toward this program are well spent and deliver a system that preserves and provides access to all types of electronic records," according to a company spokeswoman.
The GAO made several recommendations for NARA to salvage their use of EVM on the project and manage it more efficiently. Among other things, the agency recommended that NARA come up with a comprehensive EVM-based plan for all of the remaining work, improve the accuracy of the results from earned-value performance reports, and work with appropriate executives to correct persistent problems NARA has had managing ERA.
Story updated 02/08/11
Federal agencies must eliminate 800 data centers over the next five years. Find how they plan to do it in the new all-digital issue of InformationWeek Government. Download it now (registration required).
Related Reading
| To upload an avatar photo, first complete your Disqus profile. | View the list of supported HTML tags you can use to style comments. | Please read our commenting policy. | |
|
|
T-Shirt Giveaway: Each week we're selecting one great comment from our readers. The author of the comment will receive an InformaitonWeek Community t-shirt. So get posting! |
Subscribe to RSSResource Links
This Week's Issue
Free Print Subscription
SubscribeCurrent Government Issue
- Going Mobile: As federal agencies embrace devices and apps to meet employee demand, the White House seeks one comprehensive mobile strategy.
- Smartphone Security: The National Security Agency is developing technologies to make commercial devices suitable for intelligence work.
- Read the Current Issue
Technology Whitepapers
- Mobile BI: Actionable Intelligence for the Agile Enterprise
- Creating the Enterprise-Class Tablet Environment - by Yankee Group
- How To Regain IT Control In An Increasingly Mobile World - by BlackBerry
- The BlackBerry PlayBook tablet's Good Bones - by BlackBerry
- New Visual and Wizard-Driven Paradigms for Exploring Data and Developing Analytic Workflows
Featured Whitepaper
In this white paper, Tripwire discusses strategies for defending cyber threats that include monitoring security status of systems throughout the enterprise, detecting threats to sensitive data, and responding to threats in real-time.
Learn More
Featured Reports
Featured Webcasts
- Maximize ROI with Database Consolidation onto Private Clouds
- Outsourcing Security: What Every Potential Cloud Security Customer Should Know
- Server Virtualization Gets Relief From Tivoli Storage Manager for Virtual Environments
- The ABC's of Cloud Computing in the Midmarket
- Five Jobs You Can Do Better with Intelligent Decision Automation